In 100 days after project of repairing stairs from Valea Morilor park started, only eight out of 221 granite stairs has already been repaired.
Chisinau City Hall says that two out of four walls have been built and 38 more stairs has already been repaired.
At the same time, they started to built an aqueduct.
PUBLIKA.MD reminds that the project started in May and should be finished by July 2019. The project is funded by Bucharest City Hall and it costs 18 million, 970 thousand lei. Chisinau City Hall covers only 5% of the costs.