The employees of Exdrupo started to repair Ialoveni street from Durlesti, last night.
Around 20 workers started to repair the asphalt.
"We are removing the old asphalt, in order to put a new one."
The director of Exdrupo company says that they will finish in three days.
"The road is 750 meters long and 7 meters wide. Here we have 5250 square meters. We will put two asphalt layers", said Adrian Boldurescu, the director of Exdrupo company.
The driver are glad that the road will be repaired.
"The road was very bad. It was a nightmare driving here."
"It was almost impossible to drive here."
The drivers are urged to avoid Ialoveni street in the following days. The municipality promises that they will repair this road till the end of the week.